Objective | Turn a completed computer vision system to a working one |
Due date | Apr 28, 2021Â |
Key outcomes | Video streaming to ground station, detection of boxes and pylons, geolocation of pylons, distance measurement of boxes, communication between ground station and aircraft |
Status | IN PROGRESS |
Problem Statement
As we complete and unit test modules of our system, its time to start thinking of how to go from a completed system to a deployed one. This plan starts when all modules are functionally complete, but not necessarily operational.
Scope
The scope includes all activities starting from a functionally complete but not operational system. Any activities where new features are added is outside the scope of deployment.
Tasks
Operational unit | Tasks to becoming operational | Responsible individual(s) | Status |
---|---|---|---|
Relay video back to ground station | a) Flash firmware to lightbridge, setup if works. b) If above fails, setup GoPro with Vtx/VRx setups, try both. | Ryan | In progress |
Automatically detect pylons and boxes |
| Addesh, Aryan, Ray | Complete Improvement |
Communicate pylon locations, turn heading on landing and distance control on ground. |
 | Addesh/Shrinjay | In progress |
Navigate and slow aircraft on taxi |
| Atharva/Shrinjay | In progress (early) |