Flight Test Evaluation - Day Before Go/No-Go
Flight Test Evaluation - Day Before Go/No-Go
State of Competition Drone
Wiring/Harnessing:
Completed
Signal wires for wings harnessed right before flight
Motor tests complete, replaced bad ESC
All exposed connections taped over
Mechanical:
All required tasks completed and checked over
Prop clearance passed
CofG not perfectly centered, not significant issue
Systems Integration
RC Link end-to-end check completed
Motors and servos tested
Just need to do accel and compass calibration tomorrow morning
Do before wings put on
Logistics
Xierumeng driving SDC Vehicle (2 seats)
Conall has car (5 seats)
Anni - 5 seats