2023-11-12 Flight Tests
Sections for requesting team to fill out:
Admin preparation
Sections for flight test coordinator to fill out:
Flightline team
Location
Status
Drone
Sections for flightline team to fill out:
Admin Preparation
Your status should read “submitted” when you submit the FTR to our Flight Test Coordinator.
Once the coordinator approves, and a date/location/drone has been assigned, the status will change to “waiting for sub team review”. Once all sub-teams have reviewed and signed off, the status will change to “approved”
Requested By | @Hardy Yu |
---|---|
Sub-Team Review (To be checked once reviewed by sub-team representative) | Mechanical Electrical EFS Autonomy Operations |
Date of Request | Nov 9, 2023 |
Goal Summary | 4 vs 6 lipo battery endurance & Autonomy Data Collection w/ Houston |
Status? | APPROVED |
Desired Airframe | Houston / Pegasus |
Desired Date(s) | 2023-11-12 |
Testplan - to be filled out by requesting team
Flight Test Location: https://maps.app.goo.gl/XBr7u8oXZkMhzEAC8
Necessary Preparation
Necessary items:
N/A
Flight characteristics needed:
Require long flight endurance (needs more batteries)
Comms / Support needed:
TBD
Mandatory Attendees
Name | Phone # | Sub-team | Role |
---|---|---|---|
@Hardy Yu |
|
| GSO FTC |
@Yuchen Lin |
|
| PIC |
@Mihir Gupta |
|
| Autonomy Rep |
@Daniel Puratich |
|
| FTL |
[ required ] |
|
| Driver |
Flightline Team
Name | Phone # | Role | Reason |
---|---|---|---|
|
|
|
|
|
|
|
|
Pre-Flight Preparation
Checklists
Incident Procedures
Flight Test Timeline
Date/Time | Action | Notes |
---|---|---|
10:00 am | Arrive @ WARG Bay |
|
11:00 am | Briefing |
|
11:15 am | Arrival at Flight Test Location |
|
11:15 - 12: 00 | Run Pegasus 6 battery test |
|
12:05 pm | One group of ppl return to Bay charging batteries |
|
12:05 pm | Autonomy flight group run Houston Landing Recording |
|
13:20 pm | Battery charging group return to flight test location |
|
13:25 - 14: 30 pm | Run Pegasus 4 battery test |
|
15: 00pm | debrief / data analysis / food |
|