Manufacturing Timeline - 3 weeks
Categories of assembly
Assembly | Notes | DUE | DUE 2 | Project owner |
---|---|---|---|---|
H frame | rectangular CF tubing, motor mounts | Nov 27 | Dec 9 | @Conall Kingshott |
Wing Spars | entire wing spar assembly | Nov 24 | Dec 9 | @Conall Kingshott |
Wings | mostly CNC foam + control surfaces | Nov 24 | Dec 4 | @Megan Spee |
Tail | CNC foam + ctrl surfaces + mount to booms | Nov 30 | Dec 4 | @Megan Spee |
Fuselage | Cylinder body, nose/tail cones, battery compartment, bay doors | Nov 24 | Dec 9 | @Joshua Perry @Emma-Lee Keeping |
Cabin | Internal skeleton frame, stiffeners, seats | Nov 24 | Dec 9 | @Joshua Perry @Emma-Lee Keeping |
Week 1: November 13-19
Day | In progress/notes | DUE |
---|---|---|
13 sun |
|
|
14 mon | CF CRG meeting |
|
15 tue |
|
|
16 wed | Wing CNC build talk w/ Brian, can also happen thursday, w/ @Megan Spee @Conall Kingshott |
|
17 thurs |
|
|
18 fri |
|
|
19 sat | Spoke to Brian about wings @Megan Spee |
|
Week 2: November 20-26
Day | In progress/notes | DUE |
---|---|---|
20 sun |
|
|
21 mon | Wings CNC CAD done, sent to Brian |
|
22 tue |
|
|
23 wed |
|
|
24 thurs | Wings should be CNC’d next week. Brian says router is booked up, likely late next week. | Wings, wing spars, fuselage, cabin |
25 fri |
|
|
26 sat | Added Horiz stabilizer to the foam CNC parasolid file |
|
Week 3: November 27-December 2
Day | In progress/notes | DUE |
---|---|---|
27 sun |
| H frame |
28 mon |
|
|
29 tue |
|
|
30 wed |
| Tail |
1 thurs | Projected foam CNC cutting date |
|
2 fri |
|
|
3 sat |
|
|