Manufacturing Timeline - 3 weeks

Categories of assembly

Assembly

Notes

DUE

DUE 2

Project owner

Assembly

Notes

DUE

DUE 2

Project owner

H frame

rectangular CF tubing, motor mounts

Nov 27

Dec 9

@Conall Kingshott

Wing Spars

entire wing spar assembly

Nov 24

Dec 9

@Conall Kingshott

Wings

mostly CNC foam + control surfaces

Nov 24

Dec 4

@Megan Spee

Tail

CNC foam + ctrl surfaces + mount to booms

Nov 30

Dec 4

@Megan Spee

Fuselage

Cylinder body, nose/tail cones, battery compartment, bay doors

Nov 24

Dec 9

@Joshua Perry @Emma-Lee Keeping

Cabin

Internal skeleton frame, stiffeners, seats

Nov 24

Dec 9

@Joshua Perry @Emma-Lee Keeping

 

Week 1: November 13-19

Day

In progress/notes

DUE

Day

In progress/notes

DUE

13 sun

 

 

14 mon

CF CRG meeting

 

15 tue

 

 

16 wed

Wing CNC build talk w/ Brian, can also happen thursday, w/ @Megan Spee @Conall Kingshott

 

17 thurs

 

 

18 fri

 

 

19 sat

Spoke to Brian about wings @Megan Spee

 

 

Week 2: November 20-26

Day

In progress/notes

DUE

Day

In progress/notes

DUE

20 sun

 

 

21 mon

Wings CNC CAD done, sent to Brian

 

22 tue

 

 

23 wed

 

 

24 thurs

Wings should be CNC’d next week. Brian says router is booked up, likely late next week.

Wings, wing spars, fuselage, cabin

25 fri

 

 

26 sat

Added Horiz stabilizer to the foam CNC parasolid file

 

 

Week 3: November 27-December 2

Day

In progress/notes

DUE

Day

In progress/notes

DUE

27 sun

 

H frame

28 mon

 

 

29 tue

 

 

30 wed

 

Tail

1 thurs

Projected foam CNC cutting date

 

2 fri

 

 

3 sat