Timeline
(I’ll move it to a calendar but it’s just dates for right now)
Date | General | Wings | Fuselage | Controls | Boom |
---|---|---|---|---|---|
May 18 |
| Airframe outline in SolidWorks |
| Plan for controls (what can be grouped together, number of servos) | Rough CAD |
May 25 |
|
|
|
|
|
June 1 |
| Wings in SolidWorks based on how they will be manufactured (redo simulations with more detail) | Start fuselage design and how everything will connect | Plan for how controls will attach (rough CAD) |
|
June 8 |
|
|
|
|
|
June 15 |
|
| Have a fuselage done that other features can attach to | Controls added to wings |
|
June 22 |
|
|
|
|
|
June 29 | Design Review (have everything in one assembly, roughly connected) |
|
|
|
|
July 6 | Implemented design review changes |
|
|
|
|
July 13 |
|
| Plan for how electronics will sit (would be nice to have 3D printed/slots for everything) |
|
|
July 20 |
|
|
|
|
|
July 27 |
|
|
|
|
|
Aug 3 |
|
|
|
|
|
Aug 10 | Final Assembly of Plane |
|
|
|
|
Aug 17 | Manufacturing Plan → list of all materials we’ll need |
|
|
|
|
Aug 24 | Order all necessary materials |
|
|
|
|