2023-07-20 EE Meeting
General Team Status/Schedule:
Meeting times:
EE Meeting: Thursdays 7-8 PM EST E5 2103
Leads Meeting: Thursdays 9-10 PM EST E5 2103
Team Competition Aircraft Sync: Monday 7:30-8:15 PM
Attendance:
In Person | Online |
---|---|
| Jerry Parker Stanley Zen Michael Farris Ethan |
Updates this week!
Admin
No work session this weekend
Push wiring diagram project (we want to start assembling electrical at end of the term/beginning of next term)
Drone name suggestions
Flight test on the 23rd
@Michael Botros should try to host session on Sunday for footprint/altium tutorial
Active PCB Projects
High Current Power Module (Zen, Chris)
Zen: finished schematic for 12V buck, current sense and I/O
No progress from Chris
12S ESC (Ethan, Chris)
Further research conducted on high-side driving for H-bridge
Component progress from Chris. Not all footprints/symbols have been created though
Digikey Order for MCU and gate driver IC came in!
6S ESC (Mena, Rayyan)
Majority of passive components finalized
Starting on footprints in Altium
LED Controller (Neel, Parker)
Sync on Sunday
Divide work and set deadlines
ELRS Gemini (Michael, Farris)
Michael:
All schematic actions items are done, ready to start helping Farris with rough PCB placement
Farris:
Helped finish up schematic action items, started on some rough placement and basic layout
PDB (Tom)
@Michael Botros needs to check in with Tom
Tracking Antenna (Nolan, Hardy, Rukshi)
@Michael Botros should follow up on plan
12S Servo Module (Stanley, Jack, Jerry)
Stanley:
Addressed review feedback assigned to me, still working on revising buck input capacitance.
Jerry:
I need help with Altium Library
Bootcamper Progress Updates
No bootcampers currently