Flight Test Schedule Proposal

Flight Test Schedule Proposal

Initial Proposal

Initial Comments

The only pieces custom hardware that are planned on being tested so far are the ELRS Gemini TX board, LED Controller Module and the Tracking Antenna Shield (potentially).

Otherwise, electrical assembly for testing should be done to accommodate and support all other subteams for their flight tests (which basically means wiring the drone so that it can fly).

Initial Plan

Sep 16, 2023 - Have basic drone wiring setup tested (all power wiring, 2 PM02 modules in parallel) and RC and GPS

Sep 23, 2023 - Another redundancy test for the above mentioned items

Oct 7, 2023 - Undecided

Oct 21, 2023 - Test with ELRS Gemini on groundstation

Nov 4, 2023 - Another ELRS Gemini test

Nov 18, 2023 - Tracking antenna shield test with ELRS Gemini

Dec 2, 2023 - LED controller board test

Dec 16, 2023 - Undecided

Related content

July 28, 2023 Flight Test
July 28, 2023 Flight Test
More like this
2023-11-11 Flight Tests
2023-11-11 Flight Tests
More like this
2022-05-18 CV Flight Test
2022-05-18 CV Flight Test
More like this
2023-11-18 Flight Tests
2023-11-18 Flight Tests
More like this
Flight Test Schedule
Flight Test Schedule
More like this
Apr 30, 2023 Flight Test
Apr 30, 2023 Flight Test
More like this