04/27/22
Current state:
3 people in person (Steven, Aaron, Brielle)
Drone state:
arms together, landing gear and motors attached → new arm spacers left
Remaining Tasks | Deadline | Priority | Notes |
---|---|---|---|
Mount electrical components to drone | Sat April 30 | High |
|
New landing gear design to align with barrel when landing | Sun May 1 | Medium but pretty high |
|
Reprint gimbal parts | Sun May 1 | High |
|
Testing rig for Anthony | Will be completed tonight. Can drop off tomorrow. Thurs April 28 | High | Grabber can’t be mounted but shouldn’t effect axes tuning too much.
|
Spare arms | Sun May 1 | medium |
|
Spare 3D printed parts | Tues May 3 | medium |
|
Clean the bay |
| Low |
|
Fix 3D printers |
|
|
|
Make list of all 3d prints required: | April 28 |
|
|