2024-07-09 Electrical Director Sync
Attendance
@Daniel Puratich
@Neel Patel
@Jerry Tian
Summarizing Last Meeting: 2024-07-07 Electrical Director Sync
How are the projects Nolan’s managing going?
Tracking Antenna Controller: two people on it
48->12 Buck Converter: Board design done
Buck-Boost Converter: on layout, altium issues, schem is unreviewed
6S Power Module: Component Selection
Nolan’s Project Goals
Tracking Antenna Controller: getting layout going end of month rough draft
Buck-Boost Converter: rough draft end of month
6S Power Module: schematic rough draft end of month
Pegasus: Ready for flight test end of month. July 26th target electrically complete
Define which lead owns which projects clearly, during this session.
Do we wanna do this?
Is the current system very broken?
Are members getting enough mentorship to keep going?
Want to split projects more evenly?
Seems like yes
Lighting Boards @Nolan Haines with Parker → Lighting Boards on Peggy 2 Mid-September
Sensor Cluster @Nolan Haines signed NDA → Mid-fall have rev 1 boards
12S Servo Module @Jerry Tian → Test boards & assemble five of them before July 31st
6S Servo Module Rev 1 @Jerry Tian with Daniel → Assembled boards for fixed wing by end of September
ESC CAN Adapter @Nolan Haines with Daniel → not continuing after design
Unified Video System@Neel Patel → by next month Neel to figure out this project is and come up with longer term goal for discussion
GPS CAN Adapter @Nolan Haines → by next month Neel to figure out this project is and come up with longer term goal for discussion
ELRS Redundant Diversity RX @Nolan Haines → pcb end of term, validated fully by october
ZeroPilot 3.0 Hardware (ZP3HW) @Nolan Haines → integrate into fixed wing
12V->5V @ 5A Buck Converter Board @Nolan Haines with Daniel → integrate into fixed wing & houston by mid Fall term
48V->12V,8V,5V @ 3A BEC (Buck Converter) @Jerry Tian → flesh out the next rev and future of project after validating boards by mid fall term
ELRS Gemini @Nolan Haines → working boards end of term, rev 2 design completed end of F24
Tracking Antenna Electronics @Nolan Haines with Ryan → target working boards end of term
GPS Breakout @Jerry Tian ← PCB done end of month, end of September working boards to EFS
https://uwarg-docs.atlassian.net/wiki/spaces/EL/pages/2173927497 @Neel Patel → by next month Neel to figure out this project is and come up with longer term goal for discussion
https://uwarg-docs.atlassian.net/wiki/spaces/EL/pages/2578219010 @Neel Patel → by next month Neel to figure out this project is and come up with longer term goal for discussion
https://uwarg-docs.atlassian.net/wiki/spaces/EL/pages/2578448389 @Neel Patel → have something ready and tested for comp, prototype working end of F24, by next month Neel to figure out this project is and come up with longer term goal for discussion
https://uwarg-docs.atlassian.net/wiki/spaces/EL/pages/2561605642 @Nolan Haines → board design end of S24, working boards mid F24
https://uwarg-docs.atlassian.net/wiki/spaces/EL/pages/2540830830 @Jerry Tian → design custom battery system, end of F24
https://uwarg-docs.atlassian.net/wiki/spaces/EL/pages/2528509977 @Neel Patel → low priority but need a lead to pay attention
https://uwarg-docs.atlassian.net/wiki/spaces/EL/pages/2594832389/Pegasus+2+S24+EE+Assembly+Plan?search_id=f65a3965-2d30-4202-a12a-91cc57d9ce0b @Nolan Haines → peggy 2 assembled electrically end of month
Do more non-pcb projects?
More harness and validation
@Jerry Tian to scope harness and validation goals on a confluence page before F24
pcb stuff is very time consuming
better for newer members to come to sessions
Improvements to EE Meeting
Good Attendance! Up to ten people usually
Rescheduling EE meeting for lead availability
don’t wanna do this bc time works well for Nolan
Organize confluence projects however u guys want!
Delegating Tasks to PMs to relieve load on leads?
One PM for validation, one PM for harness?
no changes this term